occupied worklace

Complete redesign of an occupied workplace

How to manage an occupied workplace fit-out project that does not allow  all locations planning in advance?
The premises of a technology company are at the end of their life and need to be renovated. The company is located in 8 buildings, 70,000 m 2 . More than 5,000 employees work there. The project should last between 4 and 5 years.

Themes: Complexity, long projects, coordination, team membership

Stated goals

How to manage a project whose complexity does not allow to plan all the implementations in advance while respecting the changing constraints?

But also :

  • Limit the time spent in buffer zones for the teams whose space is being rearranged
  • Involve employee representatives in the development of proposed solutions
  • Take into account the renegotiation of the leases concerned

waitack’s answer

  • Integrate organization-specific data and initial client program
  • Create a model to optimize team zoning and work sequencing at the same time
  • Cyclically re-evaluate programming and zoning according to changes in constraints (leases, return of land, change of organization, etc.)

benefits

A fine management tool for the project team

The certainty that the proposed solutions are feasible and optimized

Continuous adaptation to delays, changes of direction and new constraints

Partners: General Contractor, Workplace Consulting